MBCI PLANT RELOCATION
Owner
Metal Building Components, L.P.
Architect
Perretz & Young Architects
Location
Ruffin Mill Road
Colonial Heights, VA
Project Size
104,000 Square Feet
Completion
July 2007
Schedule Duration
6 months

The construction of the new manufacturing facility for Metal Building Components, Inc. was completed in just six months. The plant includes a 9,500-square-foot office with mezzanine storage and totals 104,000 square feet. The building's interior and exterior finishes feature MBCI's designer metal panels.
Construction on the plant includes concrete foundations and slab that is reinforced with fiber mesh, rather than welded wire. Work for the project involved the installation of a full sprinkler system and variety of industrial equipment, including an extensive crane system for lifting up to 20 tons.
Client Testimonial: The success of this project is directly attributable to... the synergy of a well-trained team. Based on KBS's performance, dedication and commitment ot quality, I would gladly use [them] again on future construction projects."
– Donald Constantine, MBCI